Year: 2008–2009
Location: Gulf of Mexico - MC 522
Water depth: 6800 ft / 2073 m

After the Na Kika Phase 1 project was completed successfully, the Na Kika open water team returned back to Delmar to help further develop the Na Kika field in phase 2. Delmar's expertise and experience were used in planning and installing a parking pile, manifold, tuing head spool, and subsea tree. After the parking pile was installed, Delmar used its heave compensated landing system (HCLS) to install the tubing head spool, manifold, and subsea tree.

  • Installation of parking pile and other subsea assets